Boardman Lift Station Improvements
Who’s Responsible: Tony Bakken | Email: tonyb@pleasanthill.com | Phone: (816) 540-9130
Contractor: Haynes Equipment
Budget: $210,000
Project Description
The Boardman Lift Station will receive equipment replacement and upgrades of 30-year old equipment. Improvements include pump replacements including all piping, backup motors to run the lift station during loss of power, all new controls, connection to the SCADA system, and station house upgrades to include new double doors, vent louvers and wiring.
Timeline
Actual/Revised
Fall 2024 - Contract Award - COMPLETED
Spring/Summer 2025 - Construction
Completion - estimated Summer 2025
Anticipated
Fall 2024 - Contract Award
Winter 2024 - Construction
Completion - estimated Spring 2025
Current Status
March 2025 - Submittals received; equipment on order
February 2025 - Plans and reviews are expected by March 2025; pumps can be ordered after this step
09/09/24 - Council authorization