Boardman Lift Station Improvements

Who’s Responsible: Tony Bakken | Email: tonyb@pleasanthill.com | Phone: (816) 540-9130

Contractor: Haynes Equipment

Budget: $210,000

Project Description

The Boardman Lift Station will receive equipment replacement and upgrades of 30-year old equipment. Improvements include pump replacements including all piping, backup motors to run the lift station during loss of power, all new controls, connection to the SCADA system, and station house upgrades to include new double doors, vent louvers and wiring.

Timeline

Actual/Revised

  • Fall 2024 - Contract Award - COMPLETED

  • Spring/Summer 2025 - Construction

  • Completion - estimated Summer 2025

Anticipated

  • Fall 2024 - Contract Award

  • Winter 2024 - Construction

  • Completion - estimated Spring 2025

Current Status

March 2025 - Submittals received; equipment on order

February 2025 - Plans and reviews are expected by March 2025; pumps can be ordered after this step

09/09/24 - Council authorization