Country Club Drive Water Line Improvements
Who’s Responsible: Tony Bakken | Email: tonyb@pleasanthill.com | Phone: (816) 540-9130
Design: AllState Consultants
Contractor: USG - Relining; Line Replacement - TBD
Budget: Approximately $1,000,000
Project Description
The Country Club Water line has experienced a number of water main breaks and a combination of line replacement and relining is recommended for reliability of service. The line has a cast iron material from 7 Highway to Hillcrest and is slated for replacement. The material on the line east of Hillcrest is ductile iron and is slated for lining.
Timeline
Actual/Current Anticipated
Relining:
Contract Award - COMPLETED - Nov 4, 2024
Construction - March 2025
Replacement:
Planning and Design - TBD
Permitting Plan Reviews - TBD
Easements - TBD
Bidding - TBD
Construction - TBD
Completion - TBD
Anticipated
Relining:
Contract Award - TBD
Spring 2025
Replacement:
Planning and Design - estimated Winter 2024
Permitting Plan Reviews - TBD
Easements - TBD
Bidding - TBD
Construction - estimated Summer 2025
Completion - estimated Winter 2025
Current Status
February 2025: Tentatively scheduled for mid-March relining
November 2024: USG Contract signed; the relining process requires temporary water sources above the ground and weather above freezing; work will be scheduled for spring or later when temperatures are favorable
October 2024: Council approves contract with USG for SIPP relining
September 2024: City Council considers SIPP relining program