Country Club Drive Water Line Improvements

Who’s Responsible: Tony Bakken | Email: tonyb@pleasanthill.com | Phone: (816) 540-9130

Design: AllState Consultants

Contractor: USG - Relining; Line Replacement - TBD

Budget: Approximately $1,000,000

Project Description

The Country Club Water line has experienced a number of water main breaks and a combination of line replacement and relining is recommended for reliability of service. The line has a cast iron material from 7 Highway to Hillcrest and is slated for replacement. The material on the line east of Hillcrest is ductile iron and is slated for lining.

Timeline

Actual/Current Anticipated

Relining:

  • Contract Award - COMPLETED - Nov 4, 2024

  • Construction - March 2025

Replacement:

  • Planning and Design - TBD

  • Permitting Plan Reviews - TBD

  • Easements - TBD

  • Bidding - TBD

  • Construction - TBD

  • Completion - TBD

Anticipated

Relining:

  • Contract Award - TBD

  • Spring 2025

Replacement:

  • Planning and Design - estimated Winter 2024

  • Permitting Plan Reviews - TBD

  • Easements - TBD

  • Bidding - TBD

  • Construction - estimated Summer 2025

  • Completion - estimated Winter 2025

Current Status

February 2025: Tentatively scheduled for mid-March relining

November 2024: USG Contract signed; the relining process requires temporary water sources above the ground and weather above freezing; work will be scheduled for spring or later when temperatures are favorable

October 2024: Council approves contract with USG for SIPP relining

September 2024: City Council considers SIPP relining program