Project Description
The City’s engineering firm, AllState Consultants, LLC, will assist the City in the creation of a 5-year Owner’s Supervised Plan to submit to the Missouri Department of Natural Resources (DNR) to help expedite future water and sewer infrastructure improvements. The scope of work includes evaluating the existing water system; evaluating and updating the hydraulic model of the existing system and any proposed system associated with improvements identified within the plan; providing construction details and specifications as required by DNR; probable construction cost budgets with proposed projects; and coordination with DNR. This information will build upon, and where necessary, update the City’s Water Master Plan that was last completed in 2011.
Timeline
Actual/Revised
Design COMPLETED Winter 2024
DNR Review IN PROGRESS Winter 2024
Completion - Spring 2025
Anticipated
Summer 2024 - Design
DNR Review
Completion
Current Status
February 2025 - Awaiting DNR approval
January 2025 - Plans submitted to Missouri Department of Natural Resources
December 2024 - Draft plan provided for review before DNR consideration; Presentation to City Council regarding the work involved in this plan
June 2024 - Contract approved; currently in the planning phase.