Owner’s Supervised

5-Year Plan

Who’s Responsible: Tony Bakken | Email: tonyb@pleasanthill.com | Phone: (816) 540-9130

Contractor: AllState Consultants, LLC

Budget: $42,500

Project Description

The City’s engineering firm, AllState Consultants, LLC, will assist the City in the creation of a 5-year Owner’s Supervised Plan to submit to the Missouri Department of Natural Resources (DNR) to help expedite future water and sewer infrastructure improvements. The scope of work includes evaluating the existing water system; evaluating and updating the hydraulic model of the existing system and any proposed system associated with improvements identified within the plan; providing construction details and specifications as required by DNR; probable construction cost budgets with proposed projects; and coordination with DNR. This information will build upon, and where necessary, update the City’s Water Master Plan that was last completed in 2011.

Timeline

Actual/Revised

  • Design COMPLETED Winter 2024

  • DNR Review IN PROGRESS Winter 2024

  • Completion - Spring 2025

Anticipated

  • Summer 2024 - Design

  • DNR Review

  • Completion

Current Status

February 2025 - Awaiting DNR approval

January 2025 - Plans submitted to Missouri Department of Natural Resources

December 2024 - Draft plan provided for review before DNR consideration; Presentation to City Council regarding the work involved in this plan

June 2024 - Contract approved; currently in the planning phase.