Duncan North/The Oaks Lift Station Improvements

Who’s Responsible: Tony Bakken | Email: tonyb@pleasanthill.com | Phone: (816) 540-9130

Contractor: Haynes Equipment

Budget: $281,000

Project Description

The Duncan North/The Oaks Lift Station will receive equipment replacement and upgrades of 30-year old equipment. Improvements include pump replacements including all piping, backup motors to run the lift station during loss of power, all new controls, connection to the SCADA system, and station house upgrades to include new double doors, vent louvers and wiring.

Timeline

Actual/Current Anticipated

  • Contract Award COMPLETED - Fall 2024

  • Construction - Summer 2025

  • Completion - Winter 2025

Anticipated

  • Fall 2024 - Contract Award

  • Winter 2024 - Construction

  • Completion - estimated Spring 2025

Current Status

March 2025: This project may move at a different pace than the other two lift station improvements as we evaluate flow capacity, considering the future needs for this lift station; draw down tests have been completed to evaluate

February 2025: Plans and reviews are expected by March 2025; pumps can be ordered after this step

September 2024: Council authorization