Duncan North/The Oaks Lift Station Improvements
Who’s Responsible: Tony Bakken | Email: tonyb@pleasanthill.com | Phone: (816) 540-9130
Contractor: Haynes Equipment
Budget: $281,000
Project Description
The Duncan North/The Oaks Lift Station will receive equipment replacement and upgrades of 30-year old equipment. Improvements include pump replacements including all piping, backup motors to run the lift station during loss of power, all new controls, connection to the SCADA system, and station house upgrades to include new double doors, vent louvers and wiring.
Timeline
Actual/Current Anticipated
Contract Award COMPLETED - Fall 2024
Construction - Summer 2025
Completion - Winter 2025
Anticipated
Fall 2024 - Contract Award
Winter 2024 - Construction
Completion - estimated Spring 2025
Current Status
March 2025: This project may move at a different pace than the other two lift station improvements as we evaluate flow capacity, considering the future needs for this lift station; draw down tests have been completed to evaluate
February 2025: Plans and reviews are expected by March 2025; pumps can be ordered after this step
September 2024: Council authorization