Timber Street Lift Station Replacement
Who’s Responsible: Tony Bakken | Email: tonyb@pleasanthill.com | Phone: (816) 540-9130
Contractor: AllState Consultants (Survey, Design)
Budget: $220,000
Project Description
Plans call for replacing components of the Timber Street Lift Station. The lift station currently uses aged submersible pumps in a “doghouse” style enclosure. Plans include updating the pumps to ensure consistent prime and enclosing the lift station to conduct maintenance and repairs inside the structure.
The Timber Street Lift Station generally services the Cloud Jones, Glen Rae Manor, Highland Park, Ingleside addition, Old Town Village, and Tucker Smiths II subdivisions, as well as the properties located along 7 Highway in the following subdivisions (from approximately Rice Street to Delaware Street): Lexington Heights and Maple Lane addition.
Timeline
Planning and Design
5/21/24 - Engineering and survey task agreement signed
Other Governmental Approval
Bidding
Contract Award
Construction - estimated early Spring 2025
Completion
Current Status
10/07/24 - Survey completed; project is in engineering design