Timber Street Pump House Renovation

Who’s Responsible: Tony Bakken | Email: tonyb@pleasanthill.com | Phone: (816) 540-9130

Design: AllState Consultants

Contractor: Smico Contracting Group, LLC

Budget: $704,000

Project Description

The Timber Street Pump House Renovation will renovate the City’s existing drinking water pump station, which has below grade, aging pumps. The pump station provides enough pressure to pump the City’s primary water supply and drinking water storage to the elevated water tower. The goal of construction will be to replace the pumps with variable frequency drive pumps and elevate the pumps above grade. New piping, valves, and all necessary appurtenances will be installed and old piping will be removed. An additional 20 linear feet of new yard piping will be installed to create a system redundancy and provide an emergency connection for the City.

Timeline

Actual/Revised

  • Planning and Design - COMPLETED Summer 2023

  • Bidding - COMPLETED Spring 2024

  • Contract Award - COMPLETED Summer 2024

  • Construction - IN PROGRESS Summer 2024

  • Completion - estimated Spring 2025

Anticipated

  • Summer 2023 - Planning and Design COMPLETED

  • Spring 2024 - Bidding COMPLETED

  • Contract Award - Summer 2024 - COMPLETED

  • Construction - Summer 2024 - In Progress

  • Completion - estimated Spring 2025

Current Status

March 2025 - Pumps have arrived at the supplier

February 2025 - Contractor is still waiting on pumps to be delivered; temporary electrical work has been completed; VFD controls are on site; contractor is planning a full mobilization later in February

August 2024 - Work can commence; initial phases will include purchase of materials. Work is expected to be completed by April 23, 2025.