Water Tower Rehabilitation
Who’s Responsible: Tony Bakken | Email: tonyb@pleasanthill.com | Phone: (816) 540-9130
Contractor: USG
Budget: $877,000
Project Description
The City’s elevated water storage tank will be renovated to include an exterior renovation, a wet-interior renovation, dry-interior renovation, and repairs. The renovation will also include installation of an active mixer. Interior and exterior painting provides protective coatings and interior liners and the installation of the mixer circulates water for equal distribution of chemicals. The work undertaken at the water tower will not begin until the Timber Street Pump House improvements are completed.
Timeline
Summer 2023 - Contract Award COMPLETED
Construction cannot begin until at least Spring 2025
Current Status
8/19/2023 - Contract awarded; waiting completion of Timber Street Pump House renovation